  • Boxer Vehicles: ProcurementMinistry of DefenceTabled 6 Jan 2026AnsweredUIN 103516More

    Question: To ask the Secretary of State for Defence, what is the full delivery timeline for all RCH 155mm.

    Answer: The Mobile Fires Platform Project which will deliver the Remote-Controlled Howitzer 155mm (RCH 155) Calibre Wheeled Artillery System intended to be mounted on Boxer, remains in its assessment phase and is subject to contract. It is therefore too early to ...

    Answered 13 Jan 2026

    Original Parliament record
  • Delcy RodríguezForeign, Commonwealth and Development OfficeTabled 6 Jan 2026AnsweredUIN 103515More

    Question: To ask the Secretary of State for Foreign, Commonwealth and Development Affairs, whether the new Venezuelan President, Delcy Rodríguez, has had sanctions imposed upon her by the UK Government.

    Answer: I refer the Hon Member to the current list of designated persons publicly available on GOV.UK at https://www.gov.uk/government/publications/financial-sanctions-venezuela.

    Answered 12 Jan 2026

    Original Parliament record
  • Prisoner EscapesMinistry of JusticeTabled 5 Jan 2026AnsweredUIN 102962More

    Question: To ask the Secretary of State for Justice, with reference to the Urgent Question HMP Leyhill: Offender Abscondments, how many of the 57 prisoner abscondments that occurred in 2025 remained at large as of 1 January 2026.

    Answer: There were 57 absconds in the year ending March 2025. Data on absconds is published annually in the HMPPS Annual Digest: HMPPS Annual Digest 2024 to 2025 - GOV.UK. This only includes a 30-day reference point for whether prisoners remained at large. Data f...

    Answered 13 Jan 2026

    Original Parliament record
  • Firearms: LicensingHome OfficeTabled 5 Jan 2026AnsweredUIN 102961More

    Question: To ask the Secretary of State for the Home Department, what is the approval rate percentage of shotgun licence renewals within the target timeframe for Cambridgeshire Constabulary compared to the national average.

    Answer: The issuing of firearms certificates, resourcing of firearms licensing teams and the efficiency of police forces, including the timeframe taken for processing shotgun licence renewals, is a matter for individual Chief Officers of Police and Police and Cri...

    Answered 13 Jan 2026

    Original Parliament record
  • MBR Acres: Animal WelfareHome OfficeTabled 5 Jan 2026AnsweredUIN 102960More

    Question: To ask the Secretary of State for the Home Department, when was the last inspection of MBR Acres under the Animals (Scientific Procedures) Act 1986.

    Answer: The last audit at MBR Acres occurred in November 2025.The Animals in Science Regulation Unit conducts both announced and unannounced audits to assure establishments are compliant with the Animals (Scientific Procedures) Act 1986, the terms of their licenc...

    Answered 13 Jan 2026

    Original Parliament record
  • Public Sector: Facilities AgreementsCabinet OfficeTabled 5 Jan 2026AnsweredUIN 102959More

    Question: To ask the Minister for the Cabinet Office, what is the total cost of facility time in the latest period for which reporting is available, across all organisations, broken down by organisation, where that cost is paid by the public purse.

    Answer: The most recent public-sector trade union facility time data, broken down by organisation, for the period 1 April 2024 to 31 March 2025 is published here on .gov.uk.

    Answered 13 Jan 2026

    Original Parliament record
  • Ajax VehiclesMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102958More

    Question: To ask the Secretary of State for Defence, what is the range of Ajax without refuelling.

    Answer: Notwithstanding, the current reviews I can tell him that the operational range of the Ajax platform will be confirmed once the Capability Drop 4 build standard is reached, following Reliability Growth Trials.

    Answered 2 Feb 2026

    Original Parliament record
  • Artillery: ProcurementMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102957More

    Question: To ask the Secretary of State for Defence, how many RCH155 does he plan to purchase in total.

    Answer: The Mobile Fires Platform Project which will deliver the Remote-Controlled Howitzer 155mm (RCH 155) Calibre Wheeled Artillery System intended to be mounted on Boxer, remains in its assessment phase and is subject to contract. It is therefore too early to ...

    Answered 13 Jan 2026

    Original Parliament record
  • ArtilleryMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102956More

    Question: To ask the Secretary of State for Defence, how many (a) RCH155 and (b) Boxer-variants will each Royal Artillery regiment be equipped with.

    Answer: The Mobile Fires Platform Project which will deliver the Remote-Controlled Howitzer 155mm (RCH 155) Calibre Wheeled Artillery System intended to be mounted on Boxer, remains in its assessment phase and is subject to contract. It is therefore too early to ...

    Answered 13 Jan 2026

    Original Parliament record
  • Armed Forces: FirearmsMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102955More

    Question: To ask the Secretary of State for Defence, what is the out-of-service date of the M60D machine gun.

    Answer: The ramp mounted 7.62mm machine gun requirement has an Out of Service Date of 2040. This is currently fulfilled by the M60D.

    Answered 13 Jan 2026

    Original Parliament record
  • Challenger TanksMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102954More

    Question: To ask the Secretary of State for Defence, what his plans are for the 140 Challenger 2 tanks not due to be upgraded to Challenger 3.

    Answer: A decision on what will happen to the Challenger 2 platforms not being used as part of the Challenger 3 programme has not yet been taken.

    Answered 8 Jan 2026

    Original Parliament record
  • Armoured Fighting Vehicles: ProcurementMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102953More

    Question: To ask the Secretary of State for Defence, what recent progress he has made in replacing the FV430 series Mk3 Bulldog.

    Answer: The long-term replacement for the FV430 series Bulldog is being considered as part of the Heavy Protected Mobility sub-programme, within the Land Mobility Programme. The Heavy Protected Mobility sub-programme is in its Concept Phase and is currently evalu...

    Answered 8 Jan 2026

    Original Parliament record
  • Ajax Vehicles: Health and SafetyMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102952More

    Question: To ask the Secretary of State for Defence, with reference to the Written Ministerial Statement on the Ajax Investigation HCWS1212, published on 18 December 2025, how much delay to the investigations will the suspension of Ajax trials cause.

    Answer: Ongoing investigations into the safety of the Ajax platform remain on track.

    Answered 8 Jan 2026

    Original Parliament record
  • Ajax Vehicles: Health and SafetyMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102951More

    Question: To ask the Secretary of State for Defence, what was the total number of remedial tasks conducted by each unit receiving Ajax vehicles in order to make them usable on exercise as of 31 December 2025.

    Answer: All Army vehicles and equipment are subject to before use and routine maintenance schedules to ensure serviceability. Where faults are identified, these are rectified as part of business as usual activity. Information relating to each remedial task carrie...

    Answered 8 Jan 2026

    Original Parliament record
  • Army: Military IntelligenceMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102950More

    Question: To ask the Secretary of State for Defence, what assessment has he made of the feasibility of replacing the Army’s formation reconnaissance capability via Project ASGARD.

    Answer: Project ASGARD is not a replacement for the Army's formation reconnaissance capability; it enhances and improves it. It provides the digital backbone that links our reconnaissance and strike systems at machine speed. Formation reconnaissance remains essen...

    Answered 8 Jan 2026

    Original Parliament record
  • Ajax Vehicles: Health and SafetyMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102949More

    Question: To ask the Secretary of State for Defence, with reference to the Written Ministerial Statement on the Ajax Investigation (HCWS1212), published on 18th December 2025, who are the independent group of experts supporting the investigation.

    Answer: It would not be appropriate to comment on the individuals undertaking and supporting the ongoing investigations at this stage as to do so could prejudice the outcomes of the investigations. Their work is ongoing.

    Answered 13 Jan 2026

    Original Parliament record
  • Ajax Vehicles: Health and SafetyMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102948More

    Question: To ask the Secretary of State for Defence, with reference to the Written Ministerial Statement on the Ajax Investigation (HCWS1212), published on 18th December 2025, what are the 45 points of inspection each Ajax vehicle has undergone.

    Answer: The 45-point check is a comprehensive inspection of the vehicle for serviceability, functionality and condition of systems and components. It focuses on a number of areas:· Vehicle usage data.· Track and running gear, including track tension.· Driver and ...

    Answered 13 Jan 2026

    Original Parliament record
  • Armed Forces Foundation SchemeMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102947More

    Question: To ask the Secretary of State for Defence, what rank those participating in the Armed Forces Foundation Scheme will hold in the a) Army, b) Royal Navy and c) Royal Air Force.

    Answer: The Armed Forces Foundation Year Scheme (‘Gap Year’) helps deliver on the Strategic Defence Review 2025’s recommendation that Defence must offer novel ways of entry into the Armed Forces that attract more people from a wider range of backgrounds; options ...

    Answered 13 Jan 2026

    Original Parliament record
  • Armed Forces Foundation SchemeMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102946More

    Question: To ask the Secretary of State for Defence, what the projected cost of the Armed Forces Foundation Scheme is in (a) 2026-27, (b) 2027-28 and (c) 2028-29.

    Answer: The Armed Forces Foundation Year Scheme (‘Gap Year’) helps deliver on the Strategic Defence Review 2025’s recommendation that Defence must offer novel ways of entry into the Armed Forces that attract more people from a wider range of backgrounds; options ...

    Answered 13 Jan 2026

    Original Parliament record
  • Armed Forces Foundation SchemeMinistry of DefenceTabled 5 Jan 2026AnsweredUIN 102945More

    Question: To ask the Secretary of State for Defence, if he will publish the full scope of the Armed Forces Foundation Scheme for under-25s.

    Answer: The Armed Forces Foundation Year Scheme (‘Gap Year’) helps deliver on the Strategic Defence Review 2025’s recommendation that Defence must offer novel ways of entry into the Armed Forces that attract more people from a wider range of backgrounds; options ...

    Answered 13 Jan 2026

    Original Parliament record
  • Northern Ireland Troubles BillNorthern Ireland OfficeTabled 5 Jan 2026AnsweredUIN 102944More

    Question: To ask the Secretary of State for Northern Ireland, whether veterans groups were consulted on the six lawful and deliverable protections in the Northern Ireland Troubles Bill.

    Answer: The Government has announced new protections and safeguards designed specifically for veterans that were not included in the 2023 Legacy Act, and that respond directly to the views expressed by veterans during engagements that the Government has undertake...

    Answered 12 Jan 2026

    Original Parliament record
  • Challenger Tanks: ProcurementMinistry of DefenceTabled 2 Jan 2026AnsweredUIN 101931More

    Question: To ask the Secretary of State for Defence, when is the demonstration phase trial of Challenger 3 due to be completed.

    Answer: I refer the hon. Member to my answer to Question 100127, which remains extant: Challenger 3 is currently undergoing demonstration phase trials to prove the performance of the tanks. Manufacturing will begin once the tank's performance is proven, rather th...

    Answered 12 Jan 2026

    Original Parliament record
  • Local Government: CambridgeshireMinistry of Housing, Communities and Local GovernmentTabled 2 Jan 2026AnsweredUIN 101930More

    Question: To ask the Secretary of State for Housing, Communities and Local Government, what is the projected total cost of local government reorganisation in Cambridgeshire.

    Answer: Exact costs and savings will vary by area, depending on proposals received and which proposals are implemented. It was for local areas to firstly submit proposals, including estimated costs/benefits of each proposal. We anticipate that we will launch a co...

    Answered 12 Jan 2026

    Original Parliament record
  • Police and Crime CommissionersHome OfficeTabled 2 Jan 2026AnsweredUIN 101929More

    Question: To ask the Secretary of State for the Home Department, what is the projected overall financial saving from abolishing the role of Police and Crime Commissioners.

    Answer: The Government expects to save at least £100m in this Parliament as a result of abolishing Police and Crime Commissioners (PCCs).At least £20m per annum will be reinvested back into policing from 28/29, in addition to savings from cancelling future PCC el...

    Answered 13 Jan 2026

    Original Parliament record
  • Warrior VehiclesMinistry of DefenceTabled 2 Jan 2026AnsweredUIN 101928More

    Question: To ask the Secretary of State for Defence, how many Warrior armoured vehicles have been written off due to a) enemy action and b) accidents, since its introduction.

    Answer: I am unable to release the data requested as to do so would, or would be likely to, prejudice the security and capability of our Armed Forces.